1st Street Bridge Rehabilitation

Project Description:

CCG2 Cable Concrete incorporated into the Highway 1A design to serve as bank stabilization on the North and South side of Highway 1A and Park Rd. access to protect the roadside embankments in overtopping events from the adjacent Assiniboine River.

Project Location:
Brandon, Manitoba

Scope of Project:
CCG2 - 1996.54sqm or 135 Pieces

Project Install Date:
2016-10-01

Owner:
Manitoba Infrastructure and Transportation

Engineer:
Manitoba Infrastructure and Transportation

Contractor:
IECS Environmental Inc. & Titan Environmental Containment