Dunsire Estates - Mount Pleasant

Project Description:

This large overflow weir structure was built segmentally in 6 wall panels and 4 footings with a total length of 18m. The size / lifting capabilities of the contractors excavator was considered during the design stage keeping the heaviest piece under 25,000lbs.

Project Location:
Caledon, Ontario

Scope of Project:
Overflow Weir

Project Install Date:
2017-03-01

Owner:
Dunsire Estates

Engineer:
C.F. Crozier & Associates

Contractor:
Sierra Excavating