MTO 2015-3009 (Hwy 26)

Project Description:

A new 2400×2100 Concrete Box Culvert complete with wing walls was required with an open cut installation crossing Highway #26 along Georgian Bay in mid-summer. A fully precasted system allowed for an extremely efficient schedule reopening the highway for commuters in this beautiful part of the province.

Project Location:
Collingwood, Ontario

Scope of Project:
2400x2100 Concrete Box Culvert

Project Install Date:
2016-07-01

Owner:
Ministry of Transportation Ontario

Engineer:
MMM Group

Contractor:
Harold Sutherland Construction